Client: Burger King UK
Project length: 4 days
Completion date: November 2022
HF divisions involved: Electrical
Brief project description: As part of a drive towards reducing energy consumption and lowering their carbon footprint, Burger King UK wanted to switch to LED Lighting for their restaurants across the country. Our Manchester branch were contracted to carry out the electrical work for the replacement of the existing lighting system at their sites in Derby, England. This involved the disconnection and removal of their existing lighting system and the supply and install of new energy efficient LED lighting.
There are many advantages for business when upgrading to LED lighting from inefficient halogen and compact fluorescent lamps (CFL) including:
Find out more about the benefits of LED lighting upgrades using the link below.
Project Challenges: As with so much of the work we carry out in the hospitality and food sectors, it is a fast paced environment and to ensure minimal disruption for the customers on site, our electricians had to complete their work during the early hours of the day when site traffic is at its lowest. The challenge of working around both customers and staff however is something we are more than used to with the various mechanical, electrical and fire & security work we do for Pubs, Clubs, Bars & Restaurants across the UK.
At HF Group, we operate a complete Bar and Restaurant fitting service across the UK.
We supply pubs, clubs, restaurants and hotels across the country with a complete range of Electrical, Mechanical, Plumbing, Heating and Fire & Security Services.
As a leading contractor in the hospitality sector, we have worked with some of the largest pub chains and brewers in the country to fit out their latest locations across the country.
Through our group of world-class companies, all run with a family continuity at management level which is rarely seen, we can offer our customers the very best in quality and seamless integration of different services. With senior-level hands-on management from initial planning to final handover, and with the opportunity to tap into a wide range of varied services and associated consultants with a skills base and command of technologies which are second to none. Working with HF Group is more than just another service contractor.
Focussing on the Environment At HF, we are deeply committed to fostering a safer and more sustainable future, both for our company and for the communities in which we operate. As we move into October, our focus turns to one of the most pressing issues of our time: the environment. We believe that by placing […]
Did you know that there is currently an incentive grant available that can lower the up front costs of installing an EV Charge Point?
You can find out if you are eligible simply by answering some simple question.
Ready to begin? Click here